Timeline & Schedule

September 2010

Draft Watershed Management Plan issued by Fairfax Co.

October 13, 2010

Truro community attends open meeting to discuss the draft plan and the possible implications of the projects in Truro

October 21, 2010

THA comments on the possible projects in Truro identified in the Draft Plan

April 2012

THA advised that a project for restoration in the Truro parkland is in the plan for calendar year 2013

June 13, 2012

Fairfax County staff brief THA Board and residents on the potential project

July 2012

A Working Group of Truro residents is formed to be the interface between THA and the County for this project.

August 27, 2012

Meeting between the Working Group and the Fairfax County officials to discuss proposed approach and schedule

September 2012

Survey work begins in Truro

September 22, 2012

Members of the Working Group tour stream restoration projects previously completed in Reston

October 8, 2012

Letter from THA legal counsel discussing legal procedures necessary for the project to proceed

October 15. 2012

Members of the Working Group walk the Turkey Run stream in Truro with Fairfax County and design contractor personnel to review and discuss the existing stream conditions

October 16, 2012

The Working Group, Fairfax County, and the design contractor hold a pre-design meeting to discuss goals, objectives, design considerations, plans, and schedules

October 20, 2012

Members of the working group tour the recently completed restoration project on the grounds of the Fairfax Co. government center

November 8, 2012

Meeting among the Working Group, Fairfax Co., and design contractor to discuss preliminary conceptual design being developed

November 16, 2012

The Preliminary Conceptual Design is delivered by the design contractor

November 28, 2012 at 7:30 pm in the Wakefield Forest Elementary School cafeteria

Open meeting for all Truro residents to be briefed on the scope and plans for the project

December 4, 2012

Fairfax County and the design contractor to meet with the Working Group to discuss resolution of matters discussed in the November 28 meeting

December 21, 2012

The Final Conceptual Design is delivered by the design contractor

January 16, 2013 at 7:30 pm in the Wakefield Forest Elementary School cafeteria

Open meeting for all Truro residents to discuss and vote on the project based on the Final Conceptual Design

January 23, 2013

THA Board meets to decide whether to grant the easement necessary for the project to proceed

PRESUMING THE PROJECT PROCEEDS

Spring 2013

Preliminary Design completed and reviewed with the Working Group

Spring 2013

The 95% Final Design is reviewed with the Working Group

Summer 2013

Final Design completed. Permitting & construction authorization is obtained by the County

Fall 2013

Public bid process is completed for the construction contract

Winter 2013-2014

Construction complete

LONG TERM MONITORING

2-Year Plantings Warranty

Quarterly site visits by County

1-Year Contractor Workmanship Warranty

Quarterly site visits by County

County Maintenance Thereafter

Site visits annually and after significant storms or flood events.